Construct data centre at own risk: Andhra HC to developer
VIJAYAWADA: The Andhra Pradesh High Court has issued interim orders regarding the construction of the proposed Vizag Hyperscale Data Centre Park at Adavivaram and Muddarapalem villages in Visakhapatnam Rural mandal, ruling that all ongoing construction activities will remain subject to the final outcome of a Public Interest Litigation (PIL) pending before the court.
A Division Bench, comprising Chief Justice Lisa Gill and Justice Challa Gunaranjan, clarified that Vizag Hyperscale Data Centre Park Limited may proceed with the construction at its own risk, but emphasised that the company cannot claim any rights or equity in the future on the grounds of having made heavy financial investments.